Road Improvement Disruptions for A303 - A34 - M3 - M27 - WC 6th August 2018

  • Written by Editor

Travel News | Road Improvement Disruptions for A303 - A34 - M3 - M27 - WC 6th August 2018 | Andover & VillagesThe following summary of planned new and ongoing road improvements over the coming week is correct as of Friday 3 August but could be subject to change due to weather conditions or unforeseen circumstances. All Highways improvement work is carried out with the aim of causing as little disruption as possible.

M3 junctions 6 to 7 Basingstoke, Hampshire: resurfacing

Work to ensure road user safety by resurfacing a section of the M3 southbound carriageway near Basingstoke takes place this week. The M3 southbound carriageway will be closed from junction 6 to junction 7 overnight, between 9pm and 6am, on Thursday 9 August. A clearly signed diversion will be in place via Basingstoke.

M3 junction 14 Eastleigh, Hampshire: bridge maintenance

Work to ensure road user safety by maintaining the bridge which carries the M3 over the link to the M27 westbound continues this week. The link from the M3 southbound to the M27 westbound will be closed overnight, between 9pm and 6am, until Thursday 23 August. A clearly signed diversion will be in place via M27 junction 5.

In addition, the southbound entry slip road at junction 13 will be closed during the same period. A clearly signed diversion will be in place via Chilworth Roundabout, Bassett Green Road and Stoneham Way to access the M27 and M3 at junction 5.

M27 junctions 3 to 4, Hampshire: gantry signs

Work to improve journeys by maintaining gantry signs. The westbound junction 3 exit slip road will be closed overnight, between 9pm and 6am, on Thursday 9 August. A clearly signed diversion will be in place via junction 2 and return.

M4 junction 5 Brands Hill, Berkshire: litter

Works to improve journeys by litter picking litter takes place this week. The westbound entry slip road at junction 5 will be closed overnight, between 9pm and 6am, on Monday 6 August. A clearly signed diversion will be in place via London Road.

In addition the eastbound exit slip at junction 5 will be closed on the same night. A clearly signed diversion will be in place via junction 4b.

M4 junction 6 Slough, Berkshire: litter

Works to improve journeys by litter picking litter takes place this week. The eastbound exit slip at junction 6 will closed overnight, between 9pm and 6am, on Tuesday 7 August. A clearly signed diversion will be in place via junction 5 and return.

In addition the westbound entry slip road at junction 6 will be closed on the same night. A clearly signed diversion will be in place via junction 5 and return.

M4 junction 8/9 to 10 Littlefield Green, Berkshire: bridge maintenance

Work to ensure road safety by maintaining the bridge that carries the B3024 over the M4 continues this week. Two-way temporary traffic lights will be in place over the bridge from Monday 6 August for about seven weeks.

In addition the B3024 over the bridge will be fully closed overnight, between 9pm and 5am) during the same period (Monday to Friday only).

During the closures a clearly signed diversion will be in place via Waltham St Lawrence, Twyford, Shurlock Row, Warfield, Hawthorn Hill and Touchen-End. This route has been approved by the local authority for its suitability for most types of vehicles, however it is unsuitable for vehicles higher than 3.5 metres

In addition the westbound exit slip road will be closed overnight, between 9pm and 6am, on Wednesday 8 August. A clearly signed diversion will be in place via the adjacent junction.

M4 junction 10 Wokingham, Berkshire: street lighting

Work to improve journeys by maintaining the street lighting at junction 10 continues this week. The east and westbound exit slip road will be closed overnight, between 9pm and 6am, until Friday 15 August (Monday to Friday only). A clearly signed diversion will be in place via adjacent junctions and return.

M27 junction 1 Cadnam, Hampshire: bridge joint replacement

Works to replace the joints of the bridges which carry the M27 over the roundabout at junction 1 takes place this week. The M27 westbound carriageway will be closed between the slip roads at junction 1 overnight, between 9pm and 6am, on Monday 6 August. A clearly signed diversion will be in place down and across the junction

A27 Bedhampton, Hampshire: resurfacing

Work to improve journeys by resurfacing and renewing road markings the A27 starts this week. There will be a full closure of the A3(M) southbound from junction 5 to the A27 westbound carriageway overnight, between 9pm and 6am, on Monday 6 August for 4 weeks (Monday to Friday only).

All traffic will be taken off at A3(M) Junction 5. The diversion will be for all traffic to join the A27 eastbound, and exit at the following junction at Langstone (A3023) to then return westbound.

In addition the westbound entry slip road to the A27 westbound carriageway from Harts Farm will be closed during the same period.

A3 Hindhead Tunnel, Surrey: maintenance

Work to maintain the Hindhead Tunnel takes place this week, along with installing road studs. The A3 southbound will be closed from Hogs Back to the Hindhead Tunnel overnight, between 9pm and 6am, on Monday 6 August for 3 nights and then again on Friday 10 August.

In addition the A3 will be closed from Longmoor to the Hindhead Tunnel overnight, between 9pm and 6am, on Friday 10 August. A clearly signed diversion will be in place via the A325 and A31.

A3 Compton, Surrey: signs

Works to keep road users informed by maintaining the signage along the A3 near Compton takes place this week. The northbound Compton entry slip will be closed overnight, between 9pm and 6am, on Tuesday 7 August for 2 nights. A clearly signed diversion will be in place via the A31.

A34, North and South Hinksey, Oxfordshire: maintenance

Work to improve safety to road users by maintaining the carriageway takes place this week. The A34 southbound carriageway from the A423 Hinksey Hill Interchange to the A415 Marcham Interchange will be closed overnight, between 9pm and 6am, on Wednesday 8 August. A clearly signed diversion will be in place via Oxford Road, Dunmore Road, Copenhagen Drive, Colwell Drive and Marcham Road.

In addition the A34 southbound carriageway will be closed from the A420 Botley Interchange to the A423 Hinksey Hill Interchange overnight, between 9pm and 6am, on Thursday 9 August for 2 nights. A clearly signed diversion will be in place via the Oxford ring-road.

A34 Donnington, Berkshire: resurfacing

Work to improve journeys by resurfacing the A34 takes place this week. The A34 northbound from the Donnington Link to Chieveley will be closed overnight, between 9pm and 6am, on Thursday 9 August for 2 nights.

Two clearly signed diversions will be in place:

Non-motorway vehicles: from Newbury, north on the B4009 towards Hermitage, north-west along Priors Court Road towards Chieveley, then either left at Graces Lane for the service area/hotels and M4, or continue through Chieveley/Beedon for the A34 northbound

Motorway permitted vehicles: from Newbury, travel west along the A4 towards Hungerford, turn right onto the A338 towards Wantage, joining the M4 at junction 14

A34 Chieveley, Berkshire: resurfacing

Work to improve journeys by resurfacing a section of the A34 takes place this week. The northbound carriageway from Chieveley to Beedon will be closed overnight, between 9pm and 6am, on Tuesday 7 August for 2 nights. A clearly signed diversion will be in place via:

Non HGV: Graces Lane, right onto Oxford Road which then joins the A34 northbound at Beedon North HGV: M4, A338 (avoiding Wantage city centre), A417, Abingson Road and the A4130

A34 West Ilsley, Oxfordshire: resurfacing

Work to improve journeys by resurfacing a section of the A34 southbound carriageway. The A34 will be closed from the A4130 Milton Interchange to East Ilsley overnight, between 9pm and 6am, on Tuesday 7 August.

A clearly signed diversion will be in place via:

Motorway traffic: A4130, Abingdon Road, A417, A338 (avoiding Wantage city centre) and M4. Non-motorway traffic: Newbury Road, A338 (avoiding Wantage city centre), B4494 and Oxford Road

A34 Milton, Oxfordshire: resurfacing

Work to improve journeys by resurfacing a section of the A34 southbound carriageway takes place this week. The A34 from Milton Interchange to Chilton will be closed overnight, between 9pm and 6am, on Monday 6 August.

A clearly signed diversion will be in place:

Motorway traffic: A4130, Abingdon Road, A417, A338 (avoiding Wantage city centre) and M4. Non-motorway traffic: Newbury Road, A417, A338 (avoiding Wantage city centre), B4494 and Oxford Road.

A31 Wimborne Minster, Hampshire: bridge refurbishment

Work to undertake essential maintenance work to replace the joints in the bridge which carries the B3073 Oakley Hill over the A31 at Wimborne Minster continues this week. Oakley Hill across the bridge will be closed overnight, between 9pm and 6am, from Monday 6 August for 4 nights. A clearly signed diversion will be in place via Wimborne town centre and the A31.

A31 Ashley Heath, Dorset: resurfacing

Works to improve journeys by resurfacing a section of the A31 continues this week. The A31 eastbound will be closed from the Ashley Heath roundabout to Ringwood interchange overnight, between 9pm and 6am, from Monday 6 August until Friday 10 August.

A clearly signed diversion will be in place via the A338, Castle Lane East, A35 and A336.

A303 Norton, Hampshire: barrier replacement

Work to carry out essential safety barrier maintenance continues this week. The A303 eastbound will be closed from the A34 (Bullington Cross) to the Overton/Micheldever junction overnight, between 9pm and 6am, from Monday 6 August until Wednesday 15 August (Monday to Friday only). A clearly signed diversion will be in place via the A34 towards Winchester, then north on the A33.

Safety at roadworks

Highways England is working with the industry and road users to reduce the risks of working on the roads. For the safety of road workers and all road users, when you are approaching roadworks: Keep within the speed limit – it is there for your safety.

Get into the correct lane in good time – don’t keep switching.

Concentrate on the road ahead, not the roadworks.

Be alert for works’ traffic leaving or entering roadworks.

Keep a safe distance – there could be queues in front.

Observe all signs – they are there to help you.